- ›Contractor prepares and submits the Progress Claim together with all supporting documents to FQM and FPS.
Contractor
FQM
FPS
- ›FPS and FQM conduct site valuation together with PCMD for verification of completed works.
- ›The measurement record is circulated to all relevant parties for signature.
FPS
FQM
PCMD
- ›FPS prepares the Interim Valuation based on the verified and signed site measurement record.
FPS
- ›FQM reviews the Interim Valuation and issues the Payment Certificate.
FQM
- ›Contractor compiles all supporting documents including the fully signed Workdone, Interim Valuation and Payment Certificate.
- ›Complete package is formally submitted to Gamuda C&C to initiate payment.
Contractor
Gamuda C&C
Parties Involved
Contractor
FPS
FQM
PCMD
Gamuda C&C
Key Documents
Progress Claim
Workdone Record
Interim Valuation
Payment Certificate